Achievements & Activities completed to date

Lawn and Flower Garden

New type 1 subbase placed and rolled.

Clay Paving set out and being laid

Shrub bed reduce dig, subsoil/topsoil preparation and placement.

Completed rebuild of Mattock Lane brick wall and pier, and conservation work to existing brickwork and joints on Mattock Lane boundary.

Walled Garden

Completed subsoil ripping and importing of new topsoil.

Commenced forming new paths

Carried out the re-build of corner section of northern wall, and mortar/brick repairs of the walls.

Water Garden

Continued the re-grading of the lake area and commenced M&E works, including construction of pump chambers and laying of pipework, including pressure testing.

Installed scaffold to bridge to facilitate restoration work.

Commenced installation of liner membrane.

Fish Pond

Completed demolition and clearance of spoil off site

Installation of Type 1 subbase to lake base, eliminating any soft spots.

Installation of steel reinforcement and formation of concrete floor is ongoing.

Wider Park

Boundary beds topped up with imported compost and topsoil, fertilizer added and cultivation carried out.

Tree pits excavated and backfilled with specified materials.

First delivery of trees and shrubs received and planting commenced, followed by bark mulching.